World Journal of Advanced Research and Reviews, 2026, 32(02), 1511–1519
Article DOI: 10.30574/wjarr.2026.32.2.2989
Received on 10 October 2026; revised on 21 November 2026; accepted on 23 November 2026
Small food-processing enterprises frequently experience productivity losses not because of inadequate production capacity, but because of non-value-added activities embedded in routine operations. This study examines production waste at a small enterprise producing beef-stuffed tofu in Indonesia and proposes improvements to its tofu pressing process. Value stream mapping, process activity mapping, and cause-and-effect analysis were used to identify sources of non-value-added time. Waiting accounted for 133.1 min, or 90% of the identified waste; setup of the existing tofu press took approximately 31 min per production cycle. To address these losses, the study proposes a screw-driven press with an integrated handwheel, alongside 5S workplace organization. The proposed changes are estimated to reduce press setup time from 31.0 to 19.8 min (approximately 36%) and production lead time from 543.6 to 526.3 min (3.18%), without changing value-added processing time. The study demonstrates that lean improvement in small food enterprises does not necessarily require high-cost automation; targeted equipment redesign and workplace organization can reduce non-value-added time while maintaining the core production process.
Lean Manufacturing; Value Stream Mapping; Tofu Press; 5S; Set-Up Time; MSME
Preview Article PDF
Dyah Ika Rinawati and Almafadia Jauzaa. REDESIGN OF A MANUAL TOFU PRESS TO REDUCE SETUP TIME IN AN INDONESIAN FOOD MSME. World Journal of Advanced Research and Reviews, 2026, 32(02), 1511–1519. Article DOI: https://doi.org/10.30574/wjarr.2026.32.2.2989