Home
World Journal of Advanced Research and Reviews
International Journal with High Impact Factor for fast publication of Research and Review articles

Main navigation

  • Home
    • Journal Information
    • Editorial Board Members
    • Reviewer Panel
    • Abstracting and Indexing
    • Journal Policies
    • Our CrossMark Policy
    • Publication Ethics
    • Issue in Progress
    • Current Issue
    • Past Issues
    • Instructions for Authors
    • Article processing fee
    • Track Manuscript Status
    • Get Publication Certificate
    • Join Editorial Board
    • Join Reviewer Panel
  • Contact us
  • Downloads

eISSN: 2581-9615 || CODEN: WJARAI || Impact Factor 8.2 ||  CrossRef DOI

Research and review articles are invited for publication in April 2026 (Volume 30, Issue 1) Submit manuscript

Construction project management monitoring system using s-curve

Breadcrumb

  • Home
  • Construction project management monitoring system using s-curve

Joseph Dedy Irawan 1, *, Munasih 2, Maria Christina Endarwati 3, Renaldi Primaswara Prasetya 2 and Cindia Rama Auliansyah 3

1 Informatics Engineering, Faculty of Industrial Technology, National Institute of Technology Malang, Jalan Raya Karanglo km 2 Malang, Indonesia.
2 Civil engineering, Faculty of Civil Engineering and Planning, National Institute of Technology Malang, Jalan Raya Karanglo km 2 Malang, Indonesia.
3 Urban Planning, Faculty of Civil Engineering and Planning, National Institute of Technology Malang, Jalan Raya Karanglo km 2 Malang, Indonesia.
 
Research Article
World Journal of Advanced Research and Reviews, 2023, 17(02), 296-305
Article DOI: 10.30574/wjarr.2023.17.2.0231
DOI url: https://doi.org/10.30574/wjarr.2023.17.2.0231
 
Received on 22 December 2022; revised on 05 February 2023; accepted on 07 February 2023
 
Every construction project generally has a specific implementation plan and implementation schedule: when to start the implementation of the project, when to complete the project, how to do the project, and how to provide resources. Making a plan for a construction project always refers to the estimates that exist when the scheduled development plan is made. Therefore, problems can arise if there is a mismatch between the plan that has been made and its implementation. With the limited resources in the company, thorough and good planning is needed as a guide in carrying out the project to use resources efficiently and organize work to be completed according to the time specified in the contract. To achieve this goal, the manager controls the project with an s-curve by comparing the actual curve graph with the plan curve graph. The method to be used in monitoring the progress of construction projects is the s-curve. The use of the s-curve method is very supportive because it is suitable for monitoring project progress in terms of performance, cost, and timeliness of project work. The results of this study show that the construction project management monitoring website using the s-curve can create a cost budget plan that follows the contract document, a schedule plan, a weekly project report, and a project report recapitulation. The output results are displayed in the form of a Gantt Chart, and S-curves are completed with plan curve lines and realization curve lines. This project management monitoring website has a multi-user feature so that more than one user can use it. 
 
S-curve; Construction; Project; Schedule; Cost Planning; Progress
 
https://wjarr.com/sites/default/files/fulltext_pdf/WJARR-2023-0231.pdf

Preview Article PDF

Joseph Dedy Irawan, Munasih, Maria Christina Endarwati, Renaldi Primaswara Prasetya and Cindia Rama Auliansyah. Construction project management monitoring system using s-curve. World Journal of Advanced Research and Reviews, 2023, 17(2), 296-305. Article DOI: https://doi.org/10.30574/wjarr.2023.17.2.0231

Copyright © Author(s). All rights reserved. This article is published under the terms of the Creative Commons Attribution 4.0 International License (CC BY 4.0), which permits use, sharing, adaptation, distribution, and reproduction in any medium or format, as long as appropriate credit is given to the original author(s) and source, a link to the license is provided, and any changes made are indicated.


All statements, opinions, and data contained in this publication are solely those of the individual author(s) and contributor(s). The journal, editors, reviewers, and publisher disclaim any responsibility or liability for the content, including accuracy, completeness, or any consequences arising from its use.

Get Certificates

Get Publication Certificate

Download LoA

Check Corssref DOI details

Issue details

Issue Cover Page

Editorial Board

Table of content

Copyright © 2026 World Journal of Advanced Research and Reviews - All rights reserved

Developed & Designed by VS Infosolution