Home
World Journal of Advanced Research and Reviews
International Journal with High Impact Factor for fast publication of Research and Review articles

Main navigation

  • Home
    • Journal Information
    • Editorial Board Members
    • Reviewer Panel
    • Abstracting and Indexing
    • Journal Policies
    • Our CrossMark Policy
    • Publication Ethics
    • Issue in Progress
    • Current Issue
    • Past Issues
    • Instructions for Authors
    • Article processing fee
    • Track Manuscript Status
    • Get Publication Certificate
    • Join Editorial Board
    • Join Reviewer Panel
  • Contact us
  • Downloads

eISSN: 2581-9615 || CODEN: WJARAI || Impact Factor 8.2 ||  CrossRef DOI

Research and review articles are invited for publication in March 2026 (Volume 29, Issue 3) Submit manuscript

Assessing the effect of construction delivery and lead time on the performance of local road construction contractors in Lusaka district, Zambia

Breadcrumb

  • Home
  • Assessing the effect of construction delivery and lead time on the performance of local road construction contractors in Lusaka district, Zambia

Mulenga George Sampa * and Taonaziso Chowa

Department of Business Administration, Graduate School of Business, University of Zambia, Zambia.

Research Article

World Journal of Advanced Research and Reviews, 2025, 26(03), 476-493

Article DOI: 10.30574/wjarr.2025.26.3.2194

DOI url: https://doi.org/10.30574/wjarr.2025.26.3.2194

Received on 24 April 2025; revised on 31 May 2025; accepted on 03 June 2025

Contactor's expertise and performance plays an important role in successful delivery of a project. While clients want to make the best decisions in selecting the right contractor for the job, a clear understanding of the underlying attributes associated with contractors' selection in the context of achieving successful project outcomes poses to be a critical issue. The purpose of the research was to establish whether Construction delivery and lead time have an effect on the performance of Local Road Construction Contractors in Lusaka. This research used the mixed method research methodology. The research was an evaluative in nature and followed the descriptive approach and was conducted in Lusaka district of Zambia. The research used a non- experimental design to assess the effects of construction delivery and lead time on the performance of Local Road Construction Contractors in Lusaka city. The local road contractor’s performance was looked at from the perspective of quality of work and timely completion of projects. The sample consists of 54 respondents from local road contractors, chosen using data from National council of Construction, of Grade 1 to 4 of Road contractors in Lusaka and directors from government agencies using purposive sampling to select key informants. The data collected was quantitative in nature and was analyzed using Statistical Package for Social Sciences (SPSS), percentages and chi-square to establish the results to the study. Findings reviewed that there is an association between construction delivery and the quality of work and timely completion as well as between lead time and the quality of work and time timely completion of projects by the Local Road Construction Contractors in Lusaka. The research results further identified the following as reasons to why road local contractors are having challenges: 

  • Local Road Construction Contractors lack professionalism in their operations. 

  • Lack the financial capacity, human resource. 

  • Lack of sufficient support from government. 

  • The lack of expert skills and technical experience by road local contractors. 

Recommendations include: 

  • Government to help to make the business environment conducive for Local Road Construction Contractors in order for them to compete favorable with foreign contractors. 

  • A request for a call on government to amend the National Council for Construction Act No. 13 of 2003 so that it (NCC) can also regulate and punish all the erring contractors that do sub-standard jobs and those that abandon works before completion. 

Government through its partners and stakeholders should provide financial schemes for the Local Road Construction Contractors to access loans, equipment and raw materials and the necessary technical support for them to compete favorable with foreign contractors.

Project completion; Lead time management; Local Road contractors; Project cost and Construction delivery.

https://wjarr.com/sites/default/files/fulltext_pdf/WJARR-2025-2194.pdf

Preview Article PDF

Mulenga George Sampa and Taonaziso Chowa. Assessing the effect of construction delivery and lead time on the performance of local road construction contractors in Lusaka district, Zambia. World Journal of Advanced Research and Reviews, 2025, 26(3), 476-493. Article DOI: https://doi.org/10.30574/wjarr.2025.26.3.2194

Copyright © Author(s). All rights reserved. This article is published under the terms of the Creative Commons Attribution 4.0 International License (CC BY 4.0), which permits use, sharing, adaptation, distribution, and reproduction in any medium or format, as long as appropriate credit is given to the original author(s) and source, a link to the license is provided, and any changes made are indicated.


All statements, opinions, and data contained in this publication are solely those of the individual author(s) and contributor(s). The journal, editors, reviewers, and publisher disclaim any responsibility or liability for the content, including accuracy, completeness, or any consequences arising from its use.

Get Certificates

Get Publication Certificate

Download LoA

Check Corssref DOI details

Issue details

Issue Cover Page

Editorial Board

Table of content

Copyright © 2026 World Journal of Advanced Research and Reviews - All rights reserved

Developed & Designed by VS Infosolution